Managing engineering projects by managing the associated document data flows is like bulletproofing your engineering progress monitoring system. It shuts down all the avenues for wrong reporting and delayed reporting by capturing data at the source. It provides accurate information at the press of a button. Enhances timely decision-making and improves the project’s velocity. If you can manage the progress of the document workflows, then you can manage the progress of the actual work.
For example, the completion of an engineering drawing comprises the completion of;
We will get the most accurate reflection of actual work accomplished by monitoring the progression of the automated workflows associated with this engineering drawing. In this blog we will examine the ways to implement this approach to real-time Engineering Progress Monitoring & Control at an artifact level, which can be later scaled to;
In this context, your imagination is the limit. Let us see how this can be accomplished. Or If you already understood the concept and want see a live demo click here.
What is Electronic Document Management?
In its most simplistic form, Electronic Document Management Systems (EDMS) helps us to create, manage, store and retrieve documents electronically.
16 main characteristics of Electronic Document Management Systems
As we can see, good Electronic Document Management Systems have all the necessary components, if integrated well, can be transformed into real-time, error-free, cost-effective progress monitoring systems. By integrating the EDMS into a scheduling tool, EDMS can be transformed into a Powerful Progress Monitoring & Controlling system founded on the Earned Value Management (EVM) fundamentals.
Key Benefits of Progress Monitoring by integrating EDMS and EVMS are;
An Example
Stage |
Trigger |
Rules of Credit |
Planned date |
Actual date |
1 |
Completion of the engineering drawing |
50% |
20/05/2019 |
20/05/2019 |
2 |
Engineering review completion |
20% |
22/05/2019 |
22/05/2019 |
3 |
Review comments incorporation |
20% |
23/05/2019 |
|
4 |
Final review |
10% |
25/05/2019 |
|
As on 26th May 2019
As you can see, the progress reporting happens automatically as and when the work progresses. The additional step of manually entering percentage completion is eliminated. This enforces process compliance, eliminates wrong reporting, and considerably reduces waiting time for project progress information. This concept can be scaled from a document level to a work package, project, program, and portfolio level. It can be within engineering or it can be extended to procurement and construction. It can be a single location or multi-location.
Wrench Smart Project harnesses the power of Electronic Document Management and Earned Value Management systems to deliver real-time progress monitoring and has a very successful track record of more than 20 years, 9000+ projects spanning across 20 countries.
Data from the field from a very large project which implemented EDMS-based Integrated EVMS
Project details
USD 1.6 billion projects, with 120+ vendors, engineering is done in five locations, tight schedule (25 months) with incentives and penalties
Key benefits achieved